Our entire data center is going dark for 12 hours as new generators are being installed. This is the first time we've had a full power outage since moving to Exchange and I'm curious if there's anything special order or procedure to bring things
down? I was planning on bringing down both CAS/HT servers first via a regular shutdown. After that I was planning on suspending the passive copies for each database and bringing down both mailbox servers via regular shutdown. I'm looking
for some input especially with the DAG mailbox servers as to whether I need to do anything else?
↧